Which milestone is part of the Architect Phase of Ariba Methodology?

Prepare for the SAP Ariba Procurement Exam. Study using flashcards and multiple choice questions with hints and explanations to boost your confidence. Get exam-ready!

The Architect Phase of the Ariba Methodology focuses on the establishment of the project architecture and the detailed planning necessary to ensure successful implementation. During this phase, various critical milestones are established to guide the project forward.

One significant milestone in this phase is the Final Approval Meeting. This meeting serves as a pivotal point where stakeholders assess and approve the results of the design and planning work completed thus far, ensuring that the project aligns with business goals and expectations.

Additionally, the Complete User Training milestone is also relevant in the Architect Phase as preparing end users is essential for the implementation of any procurement solution. Comprehensive user training ensures that users are familiar with the new system and understand how to leverage its capabilities once it goes live.

Therefore, recognizing both the Final Approval Meeting and Complete User Training as integral elements of the Architect Phase justifies the selection of the combined option, which encompasses both milestones. This approach allows for a thorough preparation of both the project scope and the end users, setting a solid foundation for the subsequent phases of the implementation.